Dept. of Trans. PROGRESS Serial No. Contract No. 06-054-13-29 12-0H0084 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 100% 12-ORA-5-11.4/11.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-06 DEBRUIN CONSTRUCTION INC P O BOX 1355 FRENCH CAMP CA 95231 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 491,699.00 154,100.00 2.a. Extra Work b. Adjustment Comp. -4,089.95 -4,089.95 3. Materials on Hand 4. Earned Subject to Retention 487,609.05 150,010.05 5. Mobilization 120,000.00 6,000.00 6. Total Work Completed 607,609.05 7. Deductions -51,373.40 -2,553.67 8. a.Contract Retentions -24,380.45 -7,500.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 531,855.20 145,955.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,955.88