Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-11-08 12-0H0184 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 40% 12-ORA-57-20.0/20.3 Federal Project: ACST-P057(52) PH-P057(52) Progress payment No. 03 Payment period ending: 09-20-07 GRIFFITH COMPANY 2020 S YALE STREET SANTA ANA CA 92704 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 493,692.51 173,094.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 493,692.51 173,094.00 5. Mobilization 123,500.00 0.00 6. Total Work Completed 617,192.51 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 617,192.51 173,094.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,094.00