Dept. of Trans. PROGRESS Serial No. Contract No. 15-237-09-31 12-0H0344 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 57% Location: Federal Project: 12-ORA-73-25.7/28.0 NHP-P073(107) Progress payment No. 004 Payment period ending: 08-20-15 AUTOBAHN CONSTRUCTION, INC. 933 N. BATAVIA ST. ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 858,922.20 625,705.70 2. a. Extra Work 6,227.72 6,227.72 b. Adustment Comp. 3. Materials on Hand 136,378.90 43,689.31 4. Earned Subject to Retention 1,001,528.82 675,622.73 5. Mobilization 118,750.00 25,000.00 6. Total Work Completed 983,899.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,120,278.82 700,622.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 700,622.73