Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-16-35 12-0H0474 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 6% Location: Federal Project: 12-ORA-241-27.8/38.0 ACST-P241(9) Progress payment No. 003 Payment period ending: 04-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 928,555.53 224,653.38 2. a. Extra Work 13,164.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 941,719.53 224,653.38 5. Mobilization 309,103.50 0.00 6. Total Work Completed 1,250,823.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,250,823.03 224,653.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 224,653.38