Dept. of Trans. PROGRESS Serial No. Contract No. 24-169-13-47 12-0H0474 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 58% Location: Federal Project: 12-ORA-241-27.8/38.0 ACST-P241(9) Progress payment No. 027 Payment period ending: 06-20-24 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,756,418.38 1,790,631.76 2. a. Extra Work 290,353.71 77,694.45 b. Adustment Comp. 781,387.05 0.00 3. Materials on Hand 77,805.00 0.00 4. Earned Subject to Retention 12,905,964.14 1,868,326.21 5. Mobilization 618,207.00 0.00 6. Total Work Completed 13,446,366.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,524,171.14 1,868,326.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,868,326.21