Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-12-10 12-0H1504 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 6% Location: Federal Project: 12-ORA-1-4.9/5.5 NONE 12-ORA-1-10.5/14.1 Progress payment No. 001 Payment period ending: 11-20-20 SPECTRUM CONSTRUCTION GROUP INC 16 GOODYEAR #140 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 332,253.75 332,253.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 332,253.75 332,253.75 5. Mobilization 248,818.75 248,818.75 6. Total Work Completed 581,072.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 581,072.50 581,072.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 581,072.50