Dept. of Trans. PROGRESS Serial No. Contract No. 08-172-11-00 12-0H2104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 63% 12-ORA-55-17.5/ .0 Federal Project: ACNH-P055(49) Progress payment No. 13 Payment period ending: 06-20-08 F C I CONSTRUCTORS INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92009 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,570,714.20 595,235.90 2.a. Extra Work 10,710.90 -3,385.50 b. Adjustment Comp. 3. Materials on Hand 691,826.57 -182,595.28 4. Earned Subject to Retention 4,273,251.67 409,255.12 5. Mobilization 760,000.00 0.00 6. Total Work Completed 4,341,425.10 7. Deductions -21,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,012,251.67 409,255.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 409,255.12