Dept. of Trans. PROGRESS Serial No. Contract No. 08-329-09-04 12-0H2104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 92% 12-ORA-55-17.5/ .0 Federal Project: ACNH-P055(49) Progress payment No. 18 Payment period ending: 11-20-08 F C I CONSTRUCTORS INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,648,216.00 331,513.20 2.a. Extra Work 43,110.97 4,055.78 b. Adjustment Comp. 3. Materials on Hand 51,634.00 -23,282.00 4. Earned Subject to Retention 6,742,960.97 312,286.98 5. Mobilization 760,000.00 0.00 6. Total Work Completed 7,451,326.97 7. Deductions -11,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,491,960.97 312,286.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 312,286.98