Dept. of Trans. PROGRESS Serial No. Contract No. 08-297-11-11 12-0H2194 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 23% 12-ORA-261-0.0/6.3 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-08 R J NOBLE COMPANY P O BOX 620 ORANGE CA 92856 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 583,599.84 583,599.84 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 583,599.84 583,599.84 5. Mobilization 30,000.00 30,000.00 6. Total Work Completed 613,599.84 7. Deductions -937.50 -937.50 8. a.Contract Retentions -58,359.98 -58,359.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 554,302.36 554,302.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 554,302.36