Dept. of Trans. PROGRESS Serial No. Contract No. 10-172-07-45 12-0H2354 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 63% 12-ORA-5-R23.8/ .0 Federal Project: NONE Progress payment No. 07 Payment period ending: 06-20-10 R I C CONSTRUCTION CO INC 10675 E AVENUE HESPERIA CA 92345 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 547,328.55 240,700.19 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 547,328.55 240,700.19 5. Mobilization 6. Total Work Completed 547,328.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 547,328.55 240,700.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 240,700.19