Dept. of Trans. PROGRESS Serial No. Contract No. 17-082-09-11 12-0H2434 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 28% Location: Federal Project: 12-ORA-91-R0.0/R2.8 NHP-000C 427-E Progress payment No. 002 Payment period ending: 03-20-17 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 289,935.00 201,670.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 289,935.00 201,670.00 5. Mobilization 86,250.00 28,750.00 6. Total Work Completed 376,185.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 376,185.00 230,420.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,420.00