Dept. of Trans. PROGRESS Serial No. Contract No. 18-358-06-46 12-0H2704 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 0% Location: Federal Project: 12-ORA-39-9.8/10.5 ACNH-P039-0(31E) Progress payment No. 004 Payment period ending: 12-20-18 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 117,656.00 39,022.50 2. a. Extra Work 408.50 408.50 b. Adustment Comp. 3. Materials on Hand 88,060.00 1,148.46 4. Earned Subject to Retention 206,124.50 40,579.46 5. Mobilization 136,001.25 45,333.75 6. Total Work Completed 254,065.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 342,125.75 85,913.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,913.21