Dept. of Trans. PROGRESS Serial No. Contract No. 19-057-09-55 12-0H2704 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 0% Location: Federal Project: 12-ORA-39-9.8/10.5 ACNH-P039-0(31E) Progress payment No. 006 Payment period ending: 02-20-19 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 388,057.67 157,247.86 2. a. Extra Work 408.50 0.00 b. Adustment Comp. 64,312.17 64,312.17 3. Materials on Hand 24,497.70 -57,161.30 4. Earned Subject to Retention 477,276.04 164,398.73 5. Mobilization 172,268.25 36,267.00 6. Total Work Completed 625,046.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 649,544.29 200,665.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 200,665.73