Dept. of Trans. SEMI-FINAL Serial No. Contract No. 21-041-08-45 12-0H2704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-39-9.8/10.5 ACNH-P039-0(31E) Progress payment No. 023 Payment period ending: 12-31-20 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,312,609.35 -27,975.40 2. a. Extra Work 4,826.71 0.00 b. Adustment Comp. 80,424.60 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,397,860.66 -27,975.40 5. Mobilization 181,335.00 0.00 6. Total Work Completed 1,579,195.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,579,195.66 -27,975.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -27,975.40