Dept. of Trans. PROGRESS Serial No. Contract No. 09-058-08-18 12-0H5004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 100% 12-ORA-5-6.9/14.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-09 SUDHAKAR COMPANY INTERNATIONAL 1450 N FITZGERALD AVENUE RIALTO CA 92376 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,648.84 151,648.84 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 156,648.84 151,648.84 5. Mobilization 6. Total Work Completed 156,648.84 7. Deductions -39,000.00 -39,000.00 8. a.Contract Retentions -7,832.44 -7,332.44 b. Unsatisfactory Prog. -7,582.44 -7,582.44 c. Reduction after 95% Comp. 9. Total pay to Contractor 102,233.96 97,733.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,733.96