Dept. of Trans. PROGRESS Serial No. Contract No. 17-115-13-27 12-0H5304 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 40% Location: Federal Project: 12-ORA-5-6.8/6.8 ACIM-052-9(84E) Progress payment No. 004 Payment period ending: 04-20-17 UNITED ENGINEERING AND CONSTRUCTION INC 336 N CENTRAL AVE #10A GLENDALE CA 91203 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 405,032.25 120,688.00 2. a. Extra Work b. Adustment Comp. 23,087.00 23,087.00 3. Materials on Hand 4. Earned Subject to Retention 428,119.25 143,775.00 5. Mobilization 118,750.00 0.00 6. Total Work Completed 546,869.25 7. Deductions -34,294.44 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 512,574.81 143,775.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,775.00