Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-035-07-50 12-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-5-33.2/34.0 Federal Project: ACHS-X059(50) NHG-X059(50) Progress payment No. 06 Payment period ending: 10-29-10 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 341,845.20 1,493.00 2.a. Extra Work 18,313.47 11,521.91 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 360,158.67 13,014.91 5. Mobilization 20,000.00 0.00 6. Total Work Completed 380,158.67 7. Deductions 0.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 380,158.67 33,014.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,014.91