Dept. of Trans. PROGRESS Serial No. Contract No. 08-084-10-16 12-0H5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-55-6.8/7.2 Federal Project: NONE Progress payment No. 11 Payment period ending: 03-20-08 DIVERSIFIED LANDSCAPE MANAGEMENT INC 12112 SEVERN WAY RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 443,254.11 2,723.44 2.a. Extra Work 17,105.98 17,105.98 b. Adjustment Comp. -2,067.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 458,293.09 19,829.42 5. Mobilization 21,250.00 0.00 6. Total Work Completed 479,543.09 7. Deductions -5,634.00 0.00 8. a.Contract Retentions -22,914.65 -991.47 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 450,994.44 18,837.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,837.95