Dept. of Trans. PROGRESS Serial No. Contract No. 08-148-14-24 12-0H8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 100% 12-ORA-5-15.0/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-20-08 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 927111238 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 333,843.60 88,198.60 2.a. Extra Work b. Adjustment Comp. -61,907.97 -61,907.97 3. Materials on Hand 4. Earned Subject to Retention 271,935.63 26,290.63 5. Mobilization 6. Total Work Completed 271,935.63 7. Deductions 8. a.Contract Retentions -13,596.78 -1,314.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 258,338.85 24,976.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,976.10