Dept. of Trans. PROGRESS Serial No. Contract No. 15-147-07-16 12-0H9004 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 93% Location: Federal Project: 12-ORA-55-4.6/5.9 NH-P055(56) Progress payment No. 004 Payment period ending: 05-20-15 WESTCOAST PUBLIC WORK INC. 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 894,896.80 38,130.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 894,896.80 38,130.00 5. Mobilization 76,000.00 0.00 6. Total Work Completed 970,896.80 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 970,896.80 48,130.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,130.00