Dept. of Trans. PROGRESS Serial No. Contract No. 08-358-13-27 12-0J1204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 63% 12-ORA-405-8.4 Federal Project: NONE Progress payment No. 08 Payment period ending: 12-20-08 DRILL TECH DRILLING & SHORING, INC. 2200 WYMORE WAY ANTIOCH, CA 94509-8548 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 1,647,476.57 2,300.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,647,476.57 2,300.00 5. Mobilization 6. Total Work Completed 1,647,476.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,647,476.57 2,300.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,300.00