Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 25-153-07-50 12-0J34U4 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 51% Location: Federal Project: 12-ORA-5-29.6/29.6 ACNH-X059(84) 12-ORA-55-R6.4/10.3 Progress payment No. 036 Payment period ending: 05-20-25 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 82,020,011.68 1,000,611.25 2. a. Extra Work 5,301,870.72 0.00 b. Adustment Comp. 74,384.18 0.00 3. Materials on Hand 5,770,741.82 0.00 4. Earned Subject to Retention 93,167,008.40 1,000,611.25 5. Mobilization 10,858,500.00 0.00 6. Total Work Completed 98,254,766.58 7. Deductions -88,195.78 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 103,937,312.62 1,000,611.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,000,611.25