Dept. of Trans. PROGRESS Serial No. Contract No. 09-113-06-50 12-0J5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 37% 12-ORA-405-13.9/ .0 Federal Project: NONE Progress payment No. 01 Payment period ending: 04-20-09 T D S ENGINEERING 1014 S WESTLAKE BLVD 14-136 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,725.00 13,725.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 13,725.00 13,725.00 5. Mobilization 6. Total Work Completed 13,725.00 7. Deductions 8. a.Contract Retentions -1,372.50 -1,372.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,352.50 12,352.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,352.50