Dept. of Trans. PROGRESS Serial No. Contract No. 09-335-09-33 12-0J7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 44% 12-ORA-1-4.6/14.1 Federal Project: SARR-P001(541) A-P001(541) Progress payment No. 03 Payment period ending: 11-20-09 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 822,670.98 224,212.85 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 822,670.98 224,212.85 5. Mobilization 49,870.25 0.00 6. Total Work Completed 872,541.23 7. Deductions -5,484.26 -5,484.26 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 867,056.97 218,728.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 218,728.59