Dept. of Trans. PROGRESS Serial No. Contract No. 09-299-13-08 12-0J7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 53% 12-ORA-55-0.3/1.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-09 R J NOBLE COMPANY P O BOX 620 BUENA PARK CA 92856 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 146,294.59 146,294.59 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 146,294.59 146,294.59 5. Mobilization 6. Total Work Completed 146,294.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 146,294.59 146,294.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 146,294.59