Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-06-49 12-0J7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 73% 12-ORA-142-3.8/4.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-09 Y A K A R 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 91,349.00 2,100.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 91,349.00 2,100.00 5. Mobilization 6. Total Work Completed 91,349.00 7. Deductions -4,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 86,849.00 2,100.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,100.00