Dept. of Trans. PROGRESS Serial No. Contract No. 10-056-13-06 12-0J7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 95% 12-ORA-142-3.8/4.1 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-20-10 Y A K A R 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 177,508.35 32,400.00 2.a. Extra Work 13,297.75 13,297.75 b. Adjustment Comp. 48,900.00 48,900.00 3. Materials on Hand 4. Earned Subject to Retention 239,706.10 94,597.75 5. Mobilization 6. Total Work Completed 239,706.10 7. Deductions -14,500.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 225,206.10 84,597.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,597.75