Dept. of Trans. PROGRESS Serial No. Contract No. 09-334-09-39 12-0J8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 96% 12-ORA-73-12.5/12.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-09 HILLSIDE RETAINING WALLS COMPANY 5256 S MISSION RD NO 703 002 BONSALL CA 92003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 138,900.00 30,775.00 2.a. Extra Work 5,700.00 5,700.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 144,600.00 36,475.00 5. Mobilization 6,500.00 0.00 6. Total Work Completed 151,100.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 151,100.00 36,475.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,475.00