Dept. of Trans. FINAL Serial No. Contract No. 10-032-13-14 12-0J8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-5-23.6/23.9 Federal Project: NONE Progress payment No. 09 Payment period ending: 09-21-09 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 02400 Total Estimate This Estimate 1. Contract Itms Without Mobil. 868,413.54 0.00 2.a. Extra Work 38,529.00 0.00 b. Adjustment Comp. 105,737.94 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,012,680.48 0.00 5. Mobilization 6. Total Work Completed 1,012,680.48 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -43,231.68 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 43,231.68 0.00 9. Total pay to Contractor 1,012,680.48 10,000.00 10. Reduction Amt to Escrow -43,230.00 0.00 11. Payment to Escrow 43,230.00 12. Net Pymt. this Estimate 10,000.00