Dept. of Trans. PROGRESS Serial No. Contract No. 10-056-13-06 12-0K0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 57% 12-ORA-39-1.6/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-10 UNIQUE PERFORMANCE CONSTRUCTION INC 1931 NEWPORT BOULEVARD NO D COSTA MESA CA 92627 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 184,840.00 11,740.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 184,840.00 11,740.00 5. Mobilization 2,500.00 0.00 6. Total Work Completed 187,340.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 187,340.00 11,740.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,740.00