Dept. of Trans. PROGRESS Serial No. Contract No. 23-233-10-21 12-0K0214 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 70% Location: Federal Project: 12-ORA-5-12.4/14.5 ACIM-052(19) STPL-6071(103) STPL-6212(21) Progress payment No. 046 Payment period ending: 08-20-23 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,077,126.93 1,467,051.43 2. a. Extra Work 3,711,488.69 104,656.15 b. Adustment Comp. 1,591,029.08 0.00 3. Materials on Hand 1,051,222.00 -15,595.00 4. Earned Subject to Retention 84,430,866.70 1,556,112.58 5. Mobilization 10,000,000.00 0.00 6. Total Work Completed 93,379,644.70 7. Deductions -58,440.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 94,372,426.20 1,556,112.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,556,112.58