Dept. of Trans. PROGRESS Serial No. Contract No. 22-326-16-24 12-0K0224 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 54% Location: Federal Project: 12-ORA-5-14.5/17.1 TPLN-6212(22) Progress payment No. 042 Payment period ending: 11-20-22 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 83,938,446.43 1,809,475.55 2. a. Extra Work 8,734,075.46 98,920.41 b. Adustment Comp. 1,774,717.56 -31,188.00 3. Materials on Hand 1,167,502.29 -11,469.05 4. Earned Subject to Retention 95,614,741.74 1,865,738.91 5. Mobilization 12,900,000.00 0.00 6. Total Work Completed 107,347,239.45 7. Deductions -62,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 108,452,741.74 1,865,738.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,865,738.91