Dept. of Trans. PROGRESS Serial No. Contract No. 24-053-13-13 12-0K0224 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 72% Location: Federal Project: 12-ORA-5-14.5/17.1 TPLN-6212(22) Progress payment No. 057 Payment period ending: 02-20-24 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,405,303.06 551,686.15 2. a. Extra Work 15,662,679.93 569,812.03 b. Adustment Comp. 2,566,501.66 -298,566.38 3. Materials on Hand 160,407.69 -28,171.50 4. Earned Subject to Retention 124,794,892.34 794,760.30 5. Mobilization 12,900,000.00 0.00 6. Total Work Completed 137,534,484.65 7. Deductions -106,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 137,588,392.34 794,760.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 794,760.30