Dept. of Trans. PROGRESS Serial No. Contract No. 24-081-13-04 12-0K0224 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 73% Location: Federal Project: 12-ORA-5-14.5/17.1 TPLN-6212(22) Progress payment No. 058 Payment period ending: 03-20-24 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,027,041.78 621,738.71 2. a. Extra Work 16,018,192.09 355,512.16 b. Adustment Comp. 2,458,817.78 -107,683.88 3. Materials on Hand 135,821.77 -24,585.92 4. Earned Subject to Retention 125,639,873.42 844,981.07 5. Mobilization 12,900,000.00 0.00 6. Total Work Completed 138,404,051.65 7. Deductions -106,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 138,433,373.42 844,981.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 844,981.07