Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-10-58 12-0K0224 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 74% Location: Federal Project: 12-ORA-5-14.5/17.1 TPLN-6212(22) Progress payment No. 059 Payment period ending: 04-20-24 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,858,801.54 831,759.76 2. a. Extra Work 16,530,727.40 512,535.31 b. Adustment Comp. 2,351,133.90 -107,683.88 3. Materials on Hand 107,424.53 -28,397.24 4. Earned Subject to Retention 126,848,087.37 1,208,213.95 5. Mobilization 12,900,000.00 0.00 6. Total Work Completed 139,640,662.84 7. Deductions -106,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 139,641,587.37 1,208,213.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,208,213.95