Dept. of Trans. PROGRESS Serial No. Contract No. 21-263-13-55 12-0K0234 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 17% Location: Federal Project: 12-ORA-5-17.1/18.9 TPLN-6212(24) Progress payment No. 009 Payment period ending: 09-20-21 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,349,480.53 1,248,696.89 2. a. Extra Work 151,424.98 18,478.44 b. Adustment Comp. 31,564.11 0.00 3. Materials on Hand 1,480,434.76 484,280.13 4. Earned Subject to Retention 12,012,904.38 1,751,455.46 5. Mobilization 6,726,284.25 0.00 6. Total Work Completed 17,258,753.87 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,729,188.63 1,751,455.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,751,455.46