Dept. of Trans. FINAL Serial No. Contract No. 11-126-09-37 12-0K2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-73-10.2/22.5 Federal Project: SARR-P073(86) A-P073(86) Progress payment No. 12 Payment period ending: 01-13-11 R J NOBLE COMPANY P O BOX 620 ORANGE CA 928569020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,916,549.62 0.00 2.a. Extra Work 841.88 0.00 b. Adjustment Comp. 138,638.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,056,030.38 0.00 5. Mobilization 80,000.00 0.00 6. Total Work Completed 7,136,030.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,136,030.38 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00