Dept. of Trans. PROGRESS Serial No. Contract No. 10-301-09-25 12-0K2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 63% 12-ORA-1-6.6/6.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-10 TECHNO COATINGS INC 1391 S ALLEC STREET ANAHEIM CA 92805 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 83,503.70 81,764.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 83,503.70 81,764.60 5. Mobilization 19,000.00 19,000.00 6. Total Work Completed 102,503.70 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 102,503.70 100,764.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,764.60