Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-09-41 12-0K3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 64% 12-ORA-133-10.1/13.7 Federal Project: ACNH-P133(13) Progress payment No. 02 Payment period ending: 08-20-11 R J NOBLE COMPANY P O BOX 620 ORANGE CA 928659020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 749,176.77 741,076.77 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 749,176.77 741,076.77 5. Mobilization 24,225.00 24,225.00 6. Total Work Completed 773,401.77 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 773,401.77 765,301.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 765,301.77