Dept. of Trans. PROGRESS Serial No. Contract No. 25-357-09-57 12-0K91U4 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 18% Location: Federal Project: 12-ORA-91-R9.2/R11.4 ACNH-P091(156) CDSL-6212(31) Progress payment No. 009 Payment period ending: 12-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,520,946.13 2,161,244.47 2. a. Extra Work 991,251.60 32,808.52 b. Adustment Comp. 30,800.00 0.00 3. Materials on Hand 183,309.59 106,548.59 4. Earned Subject to Retention 16,726,307.32 2,300,601.58 5. Mobilization 4,159,503.91 875,685.03 6. Total Work Completed 20,702,501.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,885,811.23 3,176,286.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,176,286.61