Dept. of Trans. PROGRESS Serial No. Contract No. 26-083-12-47 12-0K93U4 PROGRESS PAYMENT VOUCHER %complete: %time: 0% 2% Location: Federal Project: 12-ORA-57-13.9/16.1 ACNH-X059(88) 12-ORA-91-4.8/6.6 CDSL-6212(33) Progress payment No. 002 Payment period ending: 03-20-26 OHLA USA, INC. 34 EXECUTIVE PARK, SUITE 180 IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 427,964.78 393,464.78 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 427,964.78 393,464.78 5. Mobilization 6. Total Work Completed 427,964.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 427,964.78 393,464.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 393,464.78