Dept. of Trans. PROGRESS Serial No. Contract No. 11-207-08-01 12-0L1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 59% 12-ORA-5-6.3/33.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-20-11 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,466.25 18,466.25 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 18,466.25 18,466.25 5. Mobilization 6. Total Work Completed 18,466.25 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,466.25 18,466.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,466.25