Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-278-11-45 12-0L1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-39-18.3/22.6 Federal Project: NONE Progress payment No. 10 Payment period ending: 06-01-12 S A K CONSTRUCTION OF CA LP 864 HOFF ROAD OFALLON MO 63366 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 379,757.00 0.00 2.a. Extra Work 129,155.58 44,464.37 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 508,912.58 44,464.37 5. Mobilization 20,000.00 0.00 6. Total Work Completed 528,912.58 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 528,912.58 44,464.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,464.37