Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-12-58 12-0L2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 89% 12-ORA-1-17.6/18.1 Federal Project: ACST-P001(557) P-P001(557) Progress payment No. 04 Payment period ending: 10-20-14 PTM GENERAL ENGINEERING SERVICES INC P O BOX 7745 RIVERSIDE CA 925137745 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 165,079.90 58,903.50 2.a. Extra Work 73,691.31 19,601.25 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 238,771.21 78,504.75 5. Mobilization 3,000.00 0.00 6. Total Work Completed 241,771.21 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 241,771.21 78,504.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 78,504.75