Dept. of Trans. SEMI-FINAL Serial No. Contract No. 13-133-14-06 12-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-1-23.7/25.9 Federal Project: NONE Progress payment No. 08 Payment period ending: 04-02-13 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 894,396.73 0.00 2.a. Extra Work 55,781.50 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 950,178.23 0.00 5. Mobilization 46,700.00 0.00 6. Total Work Completed 996,878.23 7. Deductions 0.00 11,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 996,878.23 11,500.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,500.00