Dept. of Trans. PROGRESS Serial No. Contract No. 17-083-10-16 12-0L7204 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 6% Location: Federal Project: 12-ORA-74-2.9/5.0 HSST-P P074-062(E) Progress payment No. 004 Payment period ending: 03-20-17 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 565,899.14 254,850.82 2. a. Extra Work 22,533.96 17,045.96 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 588,433.10 271,896.78 5. Mobilization 322,500.00 107,500.00 6. Total Work Completed 910,933.10 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 900,933.10 379,396.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 379,396.78