Dept. of Trans. PROGRESS Serial No. Contract No. 14-265-13-26 12-0L74U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 20% 12-ORA-55-2.0/11.8 Federal Project: HSNH-P055(54) Progress payment No. 07 Payment period ending: 09-20-14 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,128,063.02 750,834.36 2.a. Extra Work 14,776.63 0.00 b. Adjustment Comp. 27,000.16 0.00 3. Materials on Hand 0.00 -81,161.16 4. Earned Subject to Retention 3,169,839.81 669,673.20 5. Mobilization 218,500.00 46,000.00 6. Total Work Completed 3,388,339.81 7. Deductions -26.18 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,388,313.63 715,673.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 715,673.20