Dept. of Trans. PROGRESS Serial No. Contract No. 15-356-08-10 12-0L74U4 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 60% Location: Federal Project: 12-ORA-55-2.0/11.8 HSNH-P055(54) Progress payment No. 022 Payment period ending: 12-20-15 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,939,888.04 182,071.60 2. a. Extra Work 194,786.22 1,275.97 b. Adustment Comp. 63,780.48 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,198,454.74 183,347.57 5. Mobilization 230,000.00 0.00 6. Total Work Completed 14,428,454.74 7. Deductions -20,026.18 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,408,428.56 183,347.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,347.57