Dept. of Trans. PROGRESS Serial No. Contract No. 15-170-07-11 12-0L7504 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 98% Location: Federal Project: 12-ORA-91-R0.3/R0.3 HSNH-P091(138) Progress payment No. 016 Payment period ending: 06-20-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 557,140.91 15,396.80 2. a. Extra Work 28,691.61 4,108.04 b. Adustment Comp. -8,023.78 -5,313.17 3. Materials on Hand 4. Earned Subject to Retention 577,808.74 14,191.67 5. Mobilization 50,000.00 0.00 6. Total Work Completed 627,808.74 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 626,808.74 14,191.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,191.67