Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-10-53 12-0L77U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 76% 12-ORA-39-7.1/9.6 Federal Project: ACHS-P039(24) STPF-P039(24) Progress payment No. 04 Payment period ending: 05-20-14 CALIFORNIA PROFESSIONAL ELECTRIC ENGINEERING 929 OTTERBEIN AVE UNIT E LA PUENTE CA 91748 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 287,299.55 29,741.10 2.a. Extra Work b. Adjustment Comp. 7,191.00 7,191.00 3. Materials on Hand 4. Earned Subject to Retention 294,490.55 36,932.10 5. Mobilization 5,000.00 0.00 6. Total Work Completed 299,490.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -3,693.21 -3,693.21 c. Reduction after 95% Comp. 9. Total pay to Contractor 295,797.34 33,238.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,238.89